Who carries the work
around the equipment?

An equipment quote and a complete installed package can have different boundaries. Use this checklist to define responsibilities before combining vendor prices and trade estimates.

This is a review framework. Responsibility comes from the actual contract, bid documents and vendor scope; the examples below do not allocate it for your project.

Work itemResponsibility to confirmScope question
Equipment supplyOwner / vendor / contractorExact package and accessories in the quote
Delivery and unloadingTransporter / vendor / contractorDelivery point, unloading equipment and handling
FoundationsCivil / equipment contractorExcavation, concrete, anchors and templates
Setting and groutingInstaller / vendor / civilRigging, positioning, alignment and grout
Mechanical connectionsVendor / piping contractorInternal piping versus field utility connections
Electrical connectionsVendor / electrical contractorPower, controls, grounding and field termination
Supports and accessVendor / steel contractorFrames, platforms, ladders and maintenance access
FinishesVendor / specialist / contractorShop finish, field coating, insulation and repairs
Testing and start-upVendor / specialist / contractorRequired attendance, test work and temporary services

Use one row per equipment tag

Record the equipment identifier, drawing reference, vendor quote revision and the parties responsible for each activity. Mark uncertain assignments as questions requiring clarification. Do not quietly treat an unresolved item as excluded from every package.

Reconcile each package against the same basis

Compare the vendor quote, mechanical scope, electrical scope and civil or steel work using the same current documents. An item appearing in two quotations may be a legitimate split between supply and installation, or it may be a duplicate. Record the distinction.

Check temporary work and reinstatement

Permanent installation drawings may not describe all handling, access and restoration work. Include the available execution information and identify temporary arrangements that remain unconfirmed. Existing-facility work also needs a clear tie-in and demolition boundary.

Send the checklist with your estimating enquiry

Share the available equipment list, relevant vendor quotes, installation drawings and open questions. Specify whether you want a quantity takeoff, installation estimate or a coordinated package comparison.

Context: AACE's Basis of Estimate guidance discusses documenting scope, assumptions and exclusions. This checklist is our proposed review format, not an AACE-issued form.